Summit

Project Start Date: 27-10-99

Project End Date: 14-2-00

WBS TASKS Personnel E C Start Date End Date % Comp
1 SUMMIT




1.1 Mechanics




1.1.1 Instrument Modification




1.1.1.1 CAD Design jtd
11-10 19-10 67% 11-10-99 16-10-99 19-10-99
1.1.1.2 Thermal Modelling jtd mcba
19-10 25-10 86% 19-10-99 24-10-99 25-10-99
1.1.2 Structure(support)




1.1.2.1 Design jtd
25-10 4-11 36% 25-10-99 28-10-99 4-11-99
1.1.2.2 Manufacture / Install w/s jtd
4-11 9-11 33% 4-11-99 5-11-99 9-11-99
1.1.2.3 Test (Thermal) jtd
9-11 3-12 92% 9-11-99 3-12-99
1.1.3 Base (includes fins)




1.1.3.1 Design jtd
11-10 26-10 44% 11-10-99 17-10-99 26-10-99
1.1.3.2 Manufacture / Install w/s jtd
26-10 31-10 100% 26-10-99 31-10-99
1.1.3.3 Test (Thermal) map/jtd
31-10 6-12 86% 31-10-99 6-12-99
1.1.4 Thermal Insulation (Internal)




1.1.4.1 Design pgc
11-10 20-10 100% 11-10-99 20-10-99 20-10-99
1.1.4.2 Manufacture / Install pgc
20-10 30-10 36% 20-10-99 23-10-99 30-10-99
1.1.4.3 Test pgc/jtd
30-10 5-11 100% 30-10-99 5-11-99
1.1.5 Calibration Loads(modify)




1.1.5.1 Design / Specify jwvs
11-10 27-10 71% 11-10-99 22-10-99 27-10-99
1.1.5.2 Procure / Manufacture / Install pgc/jtd
27-10 2-11 29% 27-10-99 28-10-99 2-11-99
1.1.5.3 Test jtd
2-11 5-12 88% 2-11-99 5-12-99
1.1.6 Window




1.1.6.1 Design / Specify jtd/pgc
11-10 27-10 71% 11-10-99 22-10-99 27-10-99
1.1.6.2 Procure / Manufacture / Install jtd/pgc
27-10 2-11 29% 27-10-99 28-10-99 2-11-99
1.1.6.3 Test jtd/pgc
2-11 4-12 91% 2-11-99 4-12-99
1.1.7 Filter Wheel




1.1.7.1 Remove pgc
12-10 14-10 100% 12-10-99 14-10-99
1.1.8 Filter




1.1.8.1 Delivery jwvs
22-10 27-10 100% 22-10-99 27-10-99
1.1.8.2 Install pgc
27-10 4-11 44% 27-10-99 30-10-99 4-11-99
1.2 Electronics




1.2.1 Remove excess components




1.2.1.1 Document mcba/pgc
22-10 1-11 55% 22-10-99 27-10-99 1-11-99
1.2.1.2 Remove mcba
1-11 8-11 38% 1-11-99 3-11-99 8-11-99 8-11-99
1.2.2 Detector




1.2.2.1 Delivery jre
1-10 17-10 100% 1-10-99 17-10-99
1.2.2.2 Install pgc
30-10 3-11 60% 30-10-99 1-11-99 3-11-99
1.2.3 Cabling




1.2.3.1 Design mcba
14-10 26-10 15% 14-10-99 15-10-99 26-10-99
1.2.3.2 Component procurement jre
26-10 30-10 60% 26-10-99 28-10-99 30-10-99
1.2.3.3 Manufacture elec w/s
30-10 3-11 80% 30-10-99 2-11-99 3-11-99 3-11-99
1.2.3.4 Test mcba
3-11 4-11 50% 3-11-99 3-11-99 4-11-99 4-11-99
1.3 System Integration & Test




1.3.0.1 Integrate & Test All
18-11 9-12 64% 18-11-99 9-12-99