| WBS | TASKS | Personnel | E C | Start Date | End Date | % Comp | ||||
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | SUMMIT | |||||||||
| 1.1 | Mechanics | |||||||||
| 1.1.1 | Instrument Modification | |||||||||
| 1.1.1.1 | CAD Design | jtd | 11-10 | 19-10 | 67% | 11-10-99 | 16-10-99 | 19-10-99 | ||
| 1.1.1.2 | Thermal Modelling | jtd mcba | 19-10 | 25-10 | 86% | 19-10-99 | 24-10-99 | 25-10-99 | ||
| 1.1.2 | Structure(support) | |||||||||
| 1.1.2.1 | Design | jtd | 25-10 | 4-11 | 36% | 25-10-99 | 28-10-99 | 4-11-99 | ||
| 1.1.2.2 | Manufacture / Install | w/s jtd | 4-11 | 9-11 | 33% | 4-11-99 | 5-11-99 | 9-11-99 | ||
| 1.1.2.3 | Test (Thermal) | jtd | 9-11 | 3-12 | 92% | 9-11-99 | 3-12-99 | |||
| 1.1.3 | Base (includes fins) | |||||||||
| 1.1.3.1 | Design | jtd | 11-10 | 26-10 | 44% | 11-10-99 | 17-10-99 | 26-10-99 | ||
| 1.1.3.2 | Manufacture / Install | w/s jtd | 26-10 | 31-10 | 100% | 26-10-99 | 31-10-99 | |||
| 1.1.3.3 | Test (Thermal) | map/jtd | 31-10 | 6-12 | 86% | 31-10-99 | 6-12-99 | |||
| 1.1.4 | Thermal Insulation (Internal) | |||||||||
| 1.1.4.1 | Design | pgc | 11-10 | 20-10 | 100% | 11-10-99 | 20-10-99 | 20-10-99 | ||
| 1.1.4.2 | Manufacture / Install | pgc | 20-10 | 30-10 | 36% | 20-10-99 | 23-10-99 | 30-10-99 | ||
| 1.1.4.3 | Test | pgc/jtd | 30-10 | 5-11 | 100% | 30-10-99 | 5-11-99 | |||
| 1.1.5 | Calibration Loads(modify) | |||||||||
| 1.1.5.1 | Design / Specify | jwvs | 11-10 | 27-10 | 71% | 11-10-99 | 22-10-99 | 27-10-99 | ||
| 1.1.5.2 | Procure / Manufacture / Install | pgc/jtd | 27-10 | 2-11 | 29% | 27-10-99 | 28-10-99 | 2-11-99 | ||
| 1.1.5.3 | Test | jtd | 2-11 | 5-12 | 88% | 2-11-99 | 5-12-99 | |||
| 1.1.6 | Window | |||||||||
| 1.1.6.1 | Design / Specify | jtd/pgc | 11-10 | 27-10 | 71% | 11-10-99 | 22-10-99 | 27-10-99 | ||
| 1.1.6.2 | Procure / Manufacture / Install | jtd/pgc | 27-10 | 2-11 | 29% | 27-10-99 | 28-10-99 | 2-11-99 | ||
| 1.1.6.3 | Test | jtd/pgc | 2-11 | 4-12 | 91% | 2-11-99 | 4-12-99 | |||
| 1.1.7 | Filter Wheel | |||||||||
| 1.1.7.1 | Remove | pgc | 12-10 | 14-10 | 100% | 12-10-99 | 14-10-99 | |||
| 1.1.8 | Filter | |||||||||
| 1.1.8.1 | Delivery | jwvs | 22-10 | 27-10 | 100% | 22-10-99 | 27-10-99 | |||
| 1.1.8.2 | Install | pgc | 27-10 | 4-11 | 44% | 27-10-99 | 30-10-99 | 4-11-99 | ||
| 1.2 | Electronics | |||||||||
| 1.2.1 | Remove excess components | |||||||||
| 1.2.1.1 | Document | mcba/pgc | 22-10 | 1-11 | 55% | 22-10-99 | 27-10-99 | 1-11-99 | ||
| 1.2.1.2 | Remove | mcba | 1-11 | 8-11 | 38% | 1-11-99 | 3-11-99 | 8-11-99 | 8-11-99 | |
| 1.2.2 | Detector | |||||||||
| 1.2.2.1 | Delivery | jre | 1-10 | 17-10 | 100% | 1-10-99 | 17-10-99 | |||
| 1.2.2.2 | Install | pgc | 30-10 | 3-11 | 60% | 30-10-99 | 1-11-99 | 3-11-99 | ||
| 1.2.3 | Cabling | |||||||||
| 1.2.3.1 | Design | mcba | 14-10 | 26-10 | 15% | 14-10-99 | 15-10-99 | 26-10-99 | ||
| 1.2.3.2 | Component procurement | jre | 26-10 | 30-10 | 60% | 26-10-99 | 28-10-99 | 30-10-99 | ||
| 1.2.3.3 | Manufacture | elec w/s | 30-10 | 3-11 | 80% | 30-10-99 | 2-11-99 | 3-11-99 | 3-11-99 | |
| 1.2.3.4 | Test | mcba | 3-11 | 4-11 | 50% | 3-11-99 | 3-11-99 | 4-11-99 | 4-11-99 | |
| 1.3 | System Integration & Test | |||||||||
| 1.3.0.1 | Integrate & Test | All | 18-11 | 9-12 | 64% | 18-11-99 | 9-12-99 |