| WBS | TASKS | Personnel | E C | Start Date | End Date | % Comp | |||
|---|---|---|---|---|---|---|---|---|---|
| 1 | AFOS | ||||||||
| 1.1 | Mechanics | ||||||||
| 1.1.1 | F/O Modules | ||||||||
| 1.1.1.1 | Re- configure | mcba/jre | 19-10 | 26-10 | 100% | 19-10-99 | 26-10-99 | ||
| 1.1.1.2 | Document | mcba/jre | 19-10 | 8-11 | 100% | 19-10-99 | 8-11-99 | ||
| 1.1.1.3 | Test | mcba/jre | 26-10 | 3-11 | 100% | 26-10-99 | 3-11-99 | ||
| 1.2 | Optics | ||||||||
| 1.2.1 | Fibre Optics | ||||||||
| 1.2.1.1 | Remount and polish | jre | 23-10 | 16-11 | 100% | 23-10-99 | 16-11-99 | ||
| 1.2.1.2 | Test | mcba/jre | 17-11 | 5-12 | 79% | 17-11-99 | 5-12-99 | ||
| 1.3 | Electronics | ||||||||
| 1.3.1 | Boards | ||||||||
| 1.3.1.1 | Manufacture | mcba | 15-10 | 14-11 | 100% | 15-10-99 | 14-11-99 | ||
| 1.3.1.2 | Test | mcba | 15-10 | 5-12 | 92% | 15-10-99 | 5-12-99 | ||
| 1.3.2 | Racks | ||||||||
| 1.3.2.1 | Rewire | map | 12-10 | 6-11 | 100% | 12-10-99 | 6-11-99 | ||
| 1.3.2.2 | Test | map | 12-10 | 13-11 | 100% | 12-10-99 | 13-11-99 | ||
| 1.4 | Software | ||||||||
| 1.4.0.1 | Design | mcba | 9-10 | 6-12 | 92% | 9-10-99 | 6-12-99 | ||
| 1.4.0.2 | Code | mcba | 21-10 | 13-11 | 100% | 21-10-99 | 13-11-99 | ||
| 1.4.0.3 | Test | mcba | 18-11 | 5-12 | 78% | 18-11-99 | 5-12-99 | ||
| 1.5 | System Integration & Test | ||||||||
| 1.5.0.1 | Integrate & Test | mcba/jre | 11-11 | 7-12 | 78% | 11-11-99 | 7-12-99 | ||
| 2 | AASTO LABORATORY | ||||||||
| 2.1 | Pre-Shipment Tasks | ||||||||
| 2.1.1 | Thermal /Hatches | ||||||||
| 2.1.1.1 | Procurement/design heat sink | 13-10 | 20-10 | 100% | 13-10-99 | 20-10-99 | |||
| 2.1.1.2 | Hatch Design | 13-10 | 20-10 | 100% | 13-10-99 | 20-10-99 | |||
| 2.1.1.3 | Assembly | 20-10 | 1-12 | 100% | 20-10-99 | 1-12-99 | |||
| 2.1.1.4 | Test | 1-12 | 9-12 | 11% | 1-12-99 | 9-12-99 | |||
| 2.1.2 | Battery charger | ||||||||
| 2.1.2.1 | Design | JWVS | 20-10 | 7-11 | 100% | 20-10-99 | 7-11-99 | ||
| 2.1.2.2 | Manufacture | Electronics | 7-11 | 16-11 | 100% | 7-11-99 | 16-11-99 | ||
| 2.1.2.3 | Test | MAP | 16-11 | 1-12 | 100% | 16-11-99 | 1-12-99 | ||
| 2.1.3 | Web Camera(s) | ||||||||
| 2.1.3.1 | Design | MAP | 22-10 | 4-11 | 100% | 22-10-99 | 4-11-99 | ||
| 2.1.3.2 | Procure | MAP | 4-11 | 13-11 | 100% | 4-11-99 | 13-11-99 | ||
| 2.1.3.3 | Manufacture | MAP | 13-11 | 19-11 | 71% | 13-11-99 | 17-11-99 | 19-11-99 | |
| 2.1.3.4 | Test | MAP | 19-11 | 3-12 | 20% | 19-11-99 | 21-11-99 | 3-12-99 | |
| 2.2 | Post Shipment Tasks | ||||||||
| 2.2.1 | Maintenance & Detox | ||||||||
| 2.2.1.1 | Clean & Detox | 19-1 | 3-2 | 0% | 19-1-00 | 3-2-00 | |||
| 2.2.1.2 | Check TEG | 19-1 | 3-2 | 0% | 19-1-00 | 3-2-00 | |||
| 2.2.1.3 | Maintain Batteries | 19-1 | 3-2 | 0% | 19-1-00 | 3-2-00 | |||
| 2.2.2 | Installation | ||||||||
| 2.2.2.1 | Hatches | 23-1 | 4-2 | 0% | 23-1-00 | 4-2-00 | |||
| 2.2.2.2 | Equipment Racks | 24-1 | 7-2 | 0% | 24-1-00 | 7-2-00 | |||
| 2.2.2.3 | Supervisor Computer | 24-1 | 6-2 | 0% | 24-1-00 | 6-2-00 | |||
| 2.2.2.4 | Cabling | 23-1 | 10-2 | 0% | 23-1-00 | 10-2-00 | |||
| 2.2.2.5 | Video Camera | 23-1 | 9-2 | 0% | 23-1-00 | 9-2-00 | |||
| 2.2.2.6 | Battery Chargers | 22-1 | 4-2 | 0% | 22-1-00 | 4-2-00 | |||
| 2.2.2.7 | NISM | 21-1 | 4-2 | 0% | 21-1-00 | 4-2-00 | |||
| 2.2.2.8 | MISM | 21-1 | 6-2 | 0% | 21-1-00 | 6-2-00 | |||
| 2.2.2.9 | SODAR | 20-1 | 8-2 | 0% | 20-1-00 | 8-2-00 | |||
| 2.2.2.10 | SUMMIT | 18-1 | 10-2 | 0% | 18-1-00 | 10-2-00 | |||
| 2.2.2.11 | AFOS | 18-1 | 16-2 | 0% | 18-1-00 | 16-2-00 |