AFOS

Project Start Date: 27-10-99

Project End Date: 14-2-00

WBS TASKS Personnel E C Start Date End Date % Comp
1 AFOS




1.1 Mechanics




1.1.1 F/O Modules




1.1.1.1 Re- configure mcba/jre
19-10 26-10 100% 19-10-99 26-10-99
1.1.1.2 Document mcba/jre
19-10 8-11 100% 19-10-99 8-11-99
1.1.1.3 Test mcba/jre
26-10 3-11 100% 26-10-99 3-11-99
1.2 Optics




1.2.1 Fibre Optics




1.2.1.1 Remount and polish jre
23-10 16-11 100% 23-10-99 16-11-99
1.2.1.2 Test mcba/jre
17-11 5-12 79% 17-11-99 5-12-99
1.3 Electronics




1.3.1 Boards




1.3.1.1 Manufacture mcba
15-10 14-11 100% 15-10-99 14-11-99
1.3.1.2 Test mcba
15-10 5-12 92% 15-10-99 5-12-99
1.3.2 Racks




1.3.2.1 Rewire map
12-10 6-11 100% 12-10-99 6-11-99
1.3.2.2 Test map
12-10 13-11 100% 12-10-99 13-11-99
1.4 Software




1.4.0.1 Design mcba
9-10 6-12 92% 9-10-99 6-12-99
1.4.0.2 Code mcba
21-10 13-11 100% 21-10-99 13-11-99
1.4.0.3 Test mcba
18-11 5-12 78% 18-11-99 5-12-99
1.5 System Integration & Test




1.5.0.1 Integrate & Test mcba/jre
11-11 7-12 78% 11-11-99 7-12-99
2 AASTO LABORATORY




2.1 Pre-Shipment Tasks




2.1.1 Thermal /Hatches




2.1.1.1 Procurement/design heat sink

13-10 20-10 100% 13-10-99 20-10-99
2.1.1.2 Hatch Design

13-10 20-10 100% 13-10-99 20-10-99
2.1.1.3 Assembly

20-10 1-12 100% 20-10-99 1-12-99
2.1.1.4 Test

1-12 9-12 11% 1-12-99 9-12-99
2.1.2 Battery charger




2.1.2.1 Design JWVS
20-10 7-11 100% 20-10-99 7-11-99
2.1.2.2 Manufacture Electronics
7-11 16-11 100% 7-11-99 16-11-99
2.1.2.3 Test MAP
16-11 1-12 100% 16-11-99 1-12-99
2.1.3 Web Camera(s)




2.1.3.1 Design MAP
22-10 4-11 100% 22-10-99 4-11-99
2.1.3.2 Procure MAP
4-11 13-11 100% 4-11-99 13-11-99
2.1.3.3 Manufacture MAP
13-11 19-11 71% 13-11-99 17-11-99 19-11-99
2.1.3.4 Test MAP
19-11 3-12 20% 19-11-99 21-11-99 3-12-99
2.2 Post Shipment Tasks




2.2.1 Maintenance & Detox




2.2.1.1 Clean & Detox

19-1 3-2 0% 19-1-00 3-2-00
2.2.1.2 Check TEG

19-1 3-2 0% 19-1-00 3-2-00
2.2.1.3 Maintain Batteries

19-1 3-2 0% 19-1-00 3-2-00
2.2.2 Installation




2.2.2.1 Hatches

23-1 4-2 0% 23-1-00 4-2-00
2.2.2.2 Equipment Racks

24-1 7-2 0% 24-1-00 7-2-00
2.2.2.3 Supervisor Computer

24-1 6-2 0% 24-1-00 6-2-00
2.2.2.4 Cabling

23-1 10-2 0% 23-1-00 10-2-00
2.2.2.5 Video Camera

23-1 9-2 0% 23-1-00 9-2-00
2.2.2.6 Battery Chargers

22-1 4-2 0% 22-1-00 4-2-00
2.2.2.7 NISM

21-1 4-2 0% 21-1-00 4-2-00
2.2.2.8 MISM

21-1 6-2 0% 21-1-00 6-2-00
2.2.2.9 SODAR

20-1 8-2 0% 20-1-00 8-2-00
2.2.2.10 SUMMIT

18-1 10-2 0% 18-1-00 10-2-00
2.2.2.11 AFOS

18-1 16-2 0% 18-1-00 16-2-00