NISM/MISM 2000

WBS TASKS Personnel E C Start Date End Date % Comp
1 NISM/MISM




1.1 Mechanics




1.1.1 (Ball) Bearing




1.1.1.1 Design pgc
23-9 2-10 0%
1.1.1.2 Manufacture w/s
2-10 9-10 100%
1.1.1.3 Temperature Test pgc mgh
9-10 24-10 100%
1.1.1.4 Improve & debug pgc
24-10 11-11 100%
1.1.2 Rectangular Mirror Mounting




1.1.2.1 Design pgc
23-9 29-9 100%
1.1.2.2 Manufacture w/s
1-10 8-10 100%
1.1.2.3 Mounting Temperature Test pgc/mgh
8-10 18-10 100%
1.1.2.4 Install pgc/mgh
22-10 16-11 100%
1.1.3 Circular Mirror




1.1.3.1 Mounting design pgc
19-9 25-9 100%
1.1.3.2 Mounting manufacture pgc
1-10 13-10 100%
1.1.3.3 Mounting temperature test pgc
13-10 29-10 100%
1.1.4 Sealing




1.1.4.1 Test pgc
15-10 28-10 100%
1.1.4.2 Procurement jre
29-10 7-11 100%
1.1.4.3 Debug pgc
5-11 13-11 100%
1.2 Optics




1.2.1 Rectangular Mirrors




1.2.1.1 Order jre
24-9 28-9 100%
1.2.1.2 Installation pgc
1-10 11-11 100%
1.2.2 Filters




1.2.2.1 Clean / repair pgc
18-9 25-11 87%
1.2.2.2 Remount pgc
27-9 1-12 100%
1.3 Electronics




1.3.1 Chopper




1.3.1.1 Debug map
25-9 16-10 100%
1.3.1.2 Incorporate design changes map
16-10 24-10 100%
1.3.1.3 Install map
11-10 2-11 100%
1.3.1.4 Test map
2-11 25-11 100%
1.3.2 Controller racks




1.3.2.1 sub-rack rebuild map
29-9 25-10 100%
1.3.2.2 sub-rack test map
26-10 3-12 95%
1.4 Software




1.4.1 Control Software upgrade




1.4.1.1 Design mcba
4-10 8-10 100%
1.4.1.2 Code mcba
8-10 10-11 100%
1.4.1.3 Test mcba
11-11 3-12 91%
1.5 Assembly, Integration & Test




1.5.1 MISM




1.5.1.1 Mirror box pgc
30-10 3-11 100%
1.5.1.2 Detector box pgc
4-11 9-11 100%
1.5.1.3 Overall mechanical assembly pgc
9-11 13-11 100%
1.5.1.4 Electronics and cabling map
13-11 17-11 100%
1.5.1.5 Test

17-11 2-12 94%
1.5.2 NISM




1.5.2.1 mirror box pgc
30-10 4-11 100%
1.5.2.2 detector box pgc
5-11 9-11 100%
1.5.2.3 Overall mechanical assembly pgc
9-11 13-11 100%
1.5.2.4


13-11 17-11 100%
1.5.2.5 electronics and cabling map
17-11 2-12 94%
1.6 Tests




1.6.1 MISM




1.6.1.1 Sealing test pgc
20-10 25-10 100%
1.6.1.2 Detector cooler test mgh
25-10 30-10 100%
1.6.1.3 Optical alignment jre
30-10 4-11 100%
1.6.1.4 Filter Wheel jre
4-11 11-11 100%
1.6.1.5 electronics/software mcba
23-10 4-11 100%
1.6.1.6 cold temperature (up to -40°C) pgc
4-11 13-11 100%
1.6.1.7 debugging pgc/mgh
13-11 23-11 100%
1.6.2 NISM




1.6.2.1 Sealing test

18-11 29-11 100%
1.6.2.2 Detector cooler test mgh
27-10 7-11 100%
1.6.2.3 Optical alignment jre
7-11 17-11 100%
1.6.2.4 electronics/software test mcba
17-11 27-11 100%
1.6.2.5 cold temperature test pgc
17-10 16-11 100%
1.6.2.6 debugging All
17-11 29-11 100%