Operations 2000 ++

Project Start Date: 27-10-99

Project End Date: 14-2-00

WBS TASKS Personnel E C Start Date End Date % Comp
1 PROJECT MANAGEMENT




1.1 Meetings




1.1.1 Weekly Progress

15-9 23-2 48%
1.1.2 Design Reviews

22-9 18-12 80%
1.2 Documentation




1.2.1 Update Progress

15-9 1-3 28%
1.2.2 Inventory Progress

15-9 1-3 22%
1.2.3 Configuration Progress

15-9 1-3 20%
1.3 SHIPMENT




1.3.0.1 Prepare boxes/packaging MAP
24-11 10-12 35%
1.3.0.2 Identify Carriers General/Dangerous Cargo JRE/MAP
27-11 2-12 50%
1.3.0.3 Pack Equipment/ Label All
1-12 10-12 30%
1.3.0.4 Prepare and Lodge shipping documentation JRE/MAP
5-12 10-12 0%
1.3.0.5 Ship to NZ/South Pole Carrier
11-12 15-12 0%
2 NISM/MISM




2.1 Mechanics




2.1.1 (Ball) Bearing




2.1.1.1 Design pgc
23-9 2-10 0%
2.1.1.2 Manufacture w/s
2-10 9-10 100%
2.1.1.3 Temperature Test pgc mgh
9-10 24-10 100%
2.1.1.4 Improve & debug pgc
24-10 11-11 100%
2.1.2 Rectangular Mirror Mounting




2.1.2.1 Design pgc
23-9 29-9 100%
2.1.2.2 Manufacture w/s
1-10 8-10 100%
2.1.2.3 Mounting Temperature Test pgc/mgh
8-10 18-10 100%
2.1.2.4 Install pgc/mgh
22-10 16-11 100%
2.1.3 Circular Mirror




2.1.3.1 Mounting design pgc
19-9 25-9 100%
2.1.3.2 Mounting manufacture pgc
1-10 13-10 100%
2.1.3.3 Mounting temperature test pgc
13-10 29-10 100%
2.1.4 Sealing




2.1.4.1 Test pgc
15-10 28-10 100%
2.1.4.2 Procurement jre
29-10 7-11 100%
2.1.4.3 Debug pgc
5-11 13-11 100%
2.2 Optics




2.2.1 Rectangular Mirrors




2.2.1.1 Order jre
24-9 28-9 100%
2.2.1.2 Installation pgc
1-10 11-11 100%
2.2.2 Filters




2.2.2.1 Clean / repair pgc
18-9 25-11 87%
2.2.2.2 Remount pgc
27-9 1-12 98%
2.3 Electronics




2.3.1 Chopper




2.3.1.1 Debug map
25-9 16-10 100%
2.3.1.2 Incorporate design changes map
16-10 24-10 100%
2.3.1.3 Install map
11-10 2-11 100%
2.3.1.4 Test map
2-11 25-11 100%
2.3.2 Controller racks




2.3.2.1 sub-rack rebuild map
29-9 25-10 100%
2.3.2.2 sub-rack test map
26-10 3-12 92%
2.4 Software




2.4.1 Control Software upgrade




2.4.1.1 Design mcba
4-10 8-10 100%
2.4.1.2 Code mcba
8-10 10-11 100%
2.4.1.3 Test mcba
11-11 3-12 87%
2.5 Assembly, Integration & Test




2.5.1 MISM




2.5.1.1 Mirror box pgc
30-10 3-11 100%
2.5.1.2 Detector box pgc
4-11 9-11 100%
2.5.1.3 Overall mechanical assembly pgc
9-11 13-11 100%
2.5.1.4 Electronics and cabling map
13-11 17-11 100%
2.5.1.5 Test

17-11 2-12 88%
2.5.2 NISM




2.5.2.1 mirror box pgc
30-10 4-11 100%
2.5.2.2 detector box pgc
5-11 9-11 100%
2.5.2.3 Overall mechanical assembly pgc
9-11 13-11 100%
2.5.2.4


13-11 17-11 100%
2.5.2.5 electronics and cabling map
17-11 2-12 88%
2.6 Tests




2.6.1 MISM




2.6.1.1 Sealing test pgc
20-10 25-10 100%
2.6.1.2 Detector cooler test mgh
25-10 30-10 100%
2.6.1.3 Optical alignment jre
30-10 4-11 100%
2.6.1.4 Filter Wheel jre
4-11 11-11 100%
2.6.1.5 electronics/software mcba
23-10 4-11 100%
2.6.1.6 cold temperature (up to -40°C) pgc
4-11 13-11 100%
2.6.1.7 debugging pgc/mgh
13-11 23-11 100%
2.6.2 NISM




2.6.2.1 Sealing test

18-11 29-11 100%
2.6.2.2 Detector cooler test mgh
27-10 7-11 100%
2.6.2.3 Optical alignment jre
7-11 17-11 100%
2.6.2.4 electronics/software test mcba
17-11 27-11 100%
2.6.2.5 cold temperature test pgc
17-10 16-11 100%
2.6.2.6 debugging All
17-11 29-11 100%
3 SUMMIT




3.1 Mechanics




3.1.1 Instrument Modification




3.1.1.1 CAD Design jtd
11-10 19-10 67%
3.1.1.2 Thermal Modelling jtd mcba
19-10 25-10 86%
3.1.2 Structure(support)




3.1.2.1 Design jtd
25-10 4-11 36%
3.1.2.2 Manufacture / Install w/s jtd
4-11 9-11 33%
3.1.2.3 Test (Thermal) jtd
9-11 18-11 100%
3.1.3 Base (includes fins)




3.1.3.1 Design jtd
11-10 26-10 44%
3.1.3.2 Manufacture / Install w/s jtd
26-10 31-10 100%
3.1.3.3 Test (Thermal) map/jtd
31-10 20-11 100%
3.1.4 Thermal Insulation (Internal)




3.1.4.1 Design pgc
11-10 20-10 100%
3.1.4.2 Manufacture / Install pgc
20-10 30-10 36%
3.1.4.3 Test pgc/jtd
30-10 2-11 100%
3.1.5 Calibration Loads(modify)




3.1.5.1 Design / Specify jwvs
11-10 27-10 71%
3.1.5.2 Procure / Manufacture / Install pgc/jtd
27-10 2-11 29%
3.1.5.3 Test jtd
2-11 20-11 100%
3.1.6 Window




3.1.6.1 Design / Specify jtd/pgc
11-10 27-10 71%
3.1.6.2 Procure / Manufacture / Install jtd/pgc
27-10 2-11 29%
3.1.6.3 Test jtd/pgc
2-11 20-11 100%
3.1.7 Filter Wheel




3.1.7.1 Remove pgc
12-10 14-10 100%
3.1.8 Filter




3.1.8.1 Delivery jwvs
22-10 27-10 100%
3.1.8.2 Install pgc
27-10 4-11 44%
3.2 Electronics




3.2.1 Remove excess components




3.2.1.1 Document mcba/pgc
22-10 1-11 55%
3.2.1.2 Remove mcba
1-11 8-11 38%
3.2.2 Detector




3.2.2.1 Delivery jre
1-10 17-10 100%
3.2.2.2 Install pgc
30-10 3-11 60%
3.2.3 Cabling




3.2.3.1 Design mcba
14-10 26-10 15%
3.2.3.2 Component procurement jre
26-10 30-10 60%
3.2.3.3 Manufacture elec w/s
30-10 3-11 80%
3.2.3.4 Test mcba
3-11 4-11 50%
3.3 System Integration & Test




3.3.0.1 Integrate & Test All
18-11 5-12 72%
4 AFOS




4.1 Mechanics




4.1.1 F/O Modules




4.1.1.1 Re- configure mcba/jre
19-10 26-10 100%
4.1.1.2 Document mcba/jre
19-10 8-11 100%
4.1.1.3 Test mcba/jre
26-10 3-11 100%
4.2 Optics




4.2.1 Fibre Optics




4.2.1.1 Remount and polish jre
23-10 16-11 100%
4.2.1.2 Test mcba/jre
17-11 28-11 100%
4.3 Electronics




4.3.1 Boards




4.3.1.1 Manufacture mcba
15-10 8-11 100%
4.3.1.2 Test mcba
15-10 13-11 100%
4.3.2 Racks




4.3.2.1 Rewire map
12-10 6-11 100%
4.3.2.2 Test map
12-10 13-11 100%
4.4 Software




4.4.0.1 Design mcba
9-10 13-11 100%
4.4.0.2 Code mcba
21-10 13-11 100%
4.4.0.3 Test mcba
11-11 15-11 100%
4.5 System Integration & Test




4.5.0.1 Integrate & Test mcba/jre
11-11 21-11 100%
5 SODAR




5.1 Demount and Ship - UNSW

30-10 18-11 100%
5.2 Repair and Rebuild




5.2.1 Interface




5.2.1.1 Rebuild

18-11 25-11 100%
5.2.1.2 Test

25-11 1-12 86%
5.2.2 Power Supply




5.2.2.1 Rebuild

18-11 25-11 100%
5.2.2.2 Test

25-11 1-12 86%
5.3 Assemble & Integrate




5.3.0.1 Reassemble

25-11 1-12 86%
5.3.0.2 Test

1-12 4-12 0%
6 AASTO LABORATORY




6.1 Pre-Shipment Tasks




6.1.1 Thermal /Hatches




6.1.1.1 Procurement/design heat sink

13-10 20-10 100%
6.1.1.2 Hatch Design

13-10 20-10 100%
6.1.1.3 Assembly

20-10 1-12 98%
6.1.1.4 Test

1-12 9-12 0%
6.1.2 Battery charger




6.1.2.1 Design JWVS
20-10 7-11 100%
6.1.2.2 Manufacture Electronics
7-11 16-11 100%
6.1.2.3 Test MAP
16-11 1-12 94%
6.1.3 Web Camera(s)




6.1.3.1 Design MAP
22-10 4-11 100%
6.1.3.2 Procure MAP
4-11 13-11 100%
6.1.3.3 Manufacture MAP
13-11 19-11 71%
6.1.3.4 Test MAP
19-11 3-12 20%
6.2 Post Shipment Tasks




6.2.1 Maintenance & Detox




6.2.1.1 Clean & Detox

19-1 3-2 0%
6.2.1.2 Check TEG

19-1 3-2 0%
6.2.1.3 Maintain Batteries

19-1 3-2 0%
6.2.2 Installation




6.2.2.1 Hatches

23-1 4-2 0%
6.2.2.2 Equipment Racks

24-1 7-2 0%
6.2.2.3 Supervisor Computer

24-1 6-2 0%
6.2.2.4 Cabling

23-1 10-2 0%
6.2.2.5 Video Camera

23-1 9-2 0%
6.2.2.6 Battery Chargers

22-1 4-2 0%
6.2.2.7 NISM

21-1 4-2 0%
6.2.2.8 MISM

21-1 6-2 0%
6.2.2.9 SODAR

20-1 8-2 0%
6.2.2.10 SUMMIT

18-1 10-2 0%
6.2.2.11 AFOS

18-1 16-2 0%